Hocklim Engineering Pte Ltd

HOME / HOCKLIM ENGINEERING

Flood mitigation at Admiralty Road West

Explore the engineering challenge, site works and practical solutions from Hocklim’s project portfolio.

Figure 3: Setting up the ERSS
Figure 3: Setting up the ERSS

The Challenge

Repeated flash floods along Admiralty Road West disrupted traffic and access. The project required improved drainage in a coastal setting, where both rainfall and tidal water affected the work.

Figure 1: Underground Live services identified.
Figure 2: Temporary structure steel support for the live services

The Solution

Hocklim widened the existing covered box drain and built a drainage connection across Admiralty Road West. The works increased drainage capacity to help reduce flooding in the area.

Utilities management

Trial trenches and probing identified existing services before excavation. These included old British Army fuel pipes at the surface, Singtel cables, 66 kV, high-tension and low-voltage cables, and 300 mm and 1,800 mm water mains. Underground services were found at depths of 1–5 metres. Temporary steel supports, designed by the project’s professional engineer, protected them throughout construction.

Deep excavation

Deep excavation had to proceed around the live services. Earth retaining and stabilising structures (ERSS) were installed in sections to retain the surrounding soil while the services remained supported. This required careful sequencing and additional protection work.

Figure 3: Setting up the ERSS

Tidal water management

Two automated tidal gates controlled seawater entering the outlet drain. Water-level sensors activated the gates, helping the team manage tidal flow and rainwater during construction and maintain suitable working conditions for longer periods.

Figure 4: Tidal gate to control the flow of sea water

Using natural energy for site power supply

Solar panels replaced some diesel-generated power on site. They supplied the CCTV system, temporary bus stop and automated tidal gates, reducing reliance on diesel while lowering operating costs.

Figure 5: Solar panels supplying power to site systems

Traffic diversion

Hocklim revised the proposed traffic diversion from six phases to two. This reduced disruption and improved continuity of the works. The project combined deep excavation, live utility protection, tidal water management and traffic coordination.

Figure 6: Road diversion to ensure smooth traffic for the entire construction

LET’S BUILD WHAT’S NEXT

Let’s get your
project moving.

Discuss your project

HOCKLIM ENGINEERING PTE LTD

admin@hocklim.com+65 6564 5715
2025 Bukit Batok Street 23
#01-280, Singapore 659530

View original file